- Operator: Apache (55%) and Santos 45%)
- Location: North West Shelf, gas will be processed onshore at Devil Creek near Dampier
- Timeframe: Production to commence from the second half of 2011
- Cost: $800m
- Employment: Unknown during construction, 300 during production
- Status: Under construction. Clough was awarded the contract for the Engineering, procurement and fabrication of the onshore gas plant at Dampier. 40% of the gas will be piped to Perth for domestic use with the rest to go to CiticPacific’s proposed iron ore project at Cape Preston.