RioTinto has announced plans to accelerate its iron ore expansion programme in the Pilbara region with US$676 million of funding for early works and procurement.
The miner expects the expansion to bring its capacity to 333 million tonnes per year in the first half of 2015, six months earlier than planned.
It is part of a five year programme started in 2010 to increase the company’s capacity in Western Australia’s Pilbara by 50 per cent.
“Thanks to this faster pace of expansion we will be bringing extra tonnes to market earlier,” Rio Tinto chief executive, Iron Ore and Australia, Sam Walsh said.
“The demand outlook continues to be strong with supply lagging elsewhere in the industry and we are seeing new supplies proving slower to materialise than predicted.
“We are taking the opportunity to bring forward the next phase of our major capacity expansion to reap the benefits early and at no additional cost”.
The early port works include additional construction accommodation, the continuation of dredging, marine works and stockyard earth works contractors and the procurement of key equipment.
The rail-related funding will enable early engineering and accelerated procurement of long-lead items such as rail plant.
Rio will continue studies this year to determine the best mine development path to meet this schedule and conduct studies for supporting infrastructure such as utilities, fuel and accommodation.
Click for a full list of our jobs opportunities http://www.theresourcechannel.com.au/job-board?keys=rio&location=All&discipline=All&industry=All&qs=Quick+Search&level=All&class=A...
With more than 30 operating sites in Australia and a diverse range of mineral and metal mining to our name, Rio Tinto offers an array of ...
With $22 billion-worth of projects under construction or approved to start across Australia, we're looking for experienced project professionals ...
With large-scale operations in mining, refining as well as significant ports, marine and rail infrastructure, we offer a diverse range of ...
With more than 30 operating sites across Australia, the career pathways are endless for engineers at Rio Tinto. With both residential and fly-in, ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
With $22 billion of projects under construction or approved to start, we're expanding our Australian operations, and fast, which means there are ...
Ulaanbaatar, Mongolia
Oyu Tolgoi Project, Mongolia
Rio Tinto/Argyle Diamond Mine Exciting opportunity to join an Underground Block Cave Development Project Brand new equipment Great ...
by Ruby Jeer on 17 May 12
Rio Tinto is coming to New Zealand
by Ruby Jeer on 13 Apr 12
by Rio Tinto Recruitment Team on 19 Mar 12
Congratulations to our very own "Women in Resources Champion"
by Ruby Jeer on 11 Mar 12
by Ruby Jeer on 28 Feb 12
A bright future - Marandoo expansion
by David Malkin on 01 Aug 11
Rio Tinto announces expansion plans
by Rio Tinto Recruitment Team on 23 Jun 11
Brockman 4 – First Phase of Expansion
by Rio Tinto Recruitment Team on 15 Mar 11
Argyle Underground Project - Ramps Up
by David Malkin on 29 Sep 10
Update on The Argyle Underground Project
by David Malkin on 28 Jun 10